Data centres in Ireland now account for 23% of total metered electricity consumption, up from just 5% in 2015, according to recent CSO data. The figure is projected to reach 31% by 2034, giving Ireland the highest proportion of electricity used by data centres of any country in the world.
The rapid expansion over the past decade has created mounting pressure on the electricity grid, particularly in the Greater Dublin Area where most facilities are concentrated. Parts of north and west Dublin now have effectively no remaining network capacity.
Key facts
- Data centres used 23% of Ireland’s metered electricity in 2025, up from 5% in 2015
- A single modern 50 MW data centre uses nine times the total energy consumed by St James’s Hospital in 2025
- Data centre electricity demand in 2024 would power approximately 2.3 million electric cars at average Irish mileage
- Demand is forecast to rise to 31% of total electricity consumption by 2034
- Most data centres are clustered in north and west Dublin, where grid capacity is now exhausted
Grid capacity becomes shared constraint
The electricity grid has physical limits determined by the size of cables, transformers and substations, as well as operational security requirements. Network capacity is a shared public resource rather than an issue for individual projects, meaning when an area’s capacity is exhausted it affects all potential users.
Large data centres present a fundamentally different network challenge than the same annual consumption spread across many locations. The concentrated demand at single connection points has shifted power flows around which networks were originally planned.
When parts of the grid are full, even projects requiring far less power than a data centre may struggle to connect. Important future infrastructure projects in public transport and housing are among those facing potential delays in affected Dublin areas.
First come first served system under strain
The connection process operates on a first come, first served basis. Applicants contact EirGrid for large projects or ESB Networks for smaller ones, specifying their power requirements and location.
Neither EirGrid nor ESB Networks has a clear remit to prioritise one project type over another or to reserve capacity for anticipated infrastructure such as housing or public transport. Capacity built for a particular purpose can be used by another sector, with timing of application the key determining factor.
When several large data centres submit applications first, they can rapidly consume available headroom in an area. Any large demand connection, whether a data centre or other development, reduces capacity available to subsequent applicants in the same location.
IEA executive director Fatih Birol said at COP31 that the world has entered “the age of electricity”, underscoring the grid’s growing importance. Ireland now faces the challenge of managing electricity supply to support economic activity, climate action, housing development and essential infrastructure alongside unprecedented data centre demand.
Grid upgrades require substantial time and planning, but the scale and pace of demand in affected areas is unprecedented in Ireland.
Reporting based on original coverage by RTÉ News.